The financing is in place and work is ready to begin on the Printworks Mill project in Greensboro. From the Triad Business Journal:

The Alexander Co., developer of the Printworks Mill commercial and residential project across Yanceyville Street from Revolution Mill in Greensboro, will hold an official groundbreaking on the site Wednesday morning with stakeholders, local politicians and government officials on hand…

…Alexander has settled on 217 apartment units in three buildings, leaving the first floor of a four-story building near the corner of Fairview and Ninth for retail and restaurant space. He said the remaining three floors of that building, plus all seven floors of an adjoining building, will become storage space…

…plans call for the approximately 100,000 square feet of retail and storage space to be complete by June. He said the apartments, which make up the remainder of the approximately 470,000-square-foot project, are scheduled to be finished in August 2020.